Report for August 2021

Report Date
August 2021

 

Achievements in Last Period

 

  • Completion report drafted and aopproved
  • Project Closed

 

Issues/Risks
  • N/A

 

Next Steps
  • N/A

 
Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
Within Tolerance
Overall
No Change
Has formal escalation taken place?
Yes
Escalated to
Project Sponsor
Change Commentary
Some scope will be moved into follow-on project
Activity
Approved budget
227.0 days
Activity this month
1.0 day
Activity this year
1.0 day
Activity to date
175.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
System Emails & Staffmail Decommissioning
Code
ENT208
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Graeme Wood
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
14-Jan-2020
Planning Date
07-Feb-2020
Delivery Date
31-Aug-2021
Close Date
26-Aug-2021
Programme Priority
3
Overall Priority
Normal
Category
Compliance

Documentation