PLEASE NOTE THAT THIS PROCUREMENT PROJECT IS INTENTIONALLY SECURE AND UNPUBLISHED.

Procurement, configuration and deployment of HCI

The project documentation will be held on the Project Sharepoint  (https://uoe.sharepoint.com/sites/ITI-Projects/Enterprise%20Infrastructure%20Procurement/Shared%20Documents/Forms/AllItems.aspx) and only necessary data and reports on this project website.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
May 2021 GREEN 129.0 days 128.0 days 21.0

Project Info

Project
Enterprise Infrastructure Procurement
Code
ENT301
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Graeme Wood
Current Stage
Plan
Status
In Progress
Project Classification
Transform
Start Date
09-Oct-2020
Planning Date
07-May-2021
Delivery Date
16-Jul-2022
Close Date
31-Jul-2021
Overall Priority
Highest
Category
Discretionary

Documentation

Not available.

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.