Project Decision Log

   
   
   

Decisions and the Changes to Scope/Budget/Time/Quality/Objectives

Describe Decision

(detail of decision and any alternatives discussed)

 

Made by

 

Date  

 

 

Impact on Scope / Objective  

 

 

Associated Risk

 

 

 

   

 

 

 

 

 

 

   

 

 

 

 

 

 

   

 

 

 

 

 

 

   

 

 

 

 

 

 

   

 

 

 

Project Info

Project
Enterprise Infrastructure Migrations and Infrastructure Upgrade Completion
Code
ENT401
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Maurice Franceschi
Project Sponsor
Graeme Wood
Current Stage
Execute
Status
In Progress
Project Classification
Transform
Start Date
12-Sep-2022
Planning Date
18-Nov-2022
Delivery Date
30-Jun-2023
Close Date
28-Jul-2023
Overall Priority
Highest

Documentation

Plan