Due to staff changes, the code which underpins the provisioning of accounts in Active Directory and the account provisioning on Office 365 now not fully understood or documented. This project will aim to document the code, hand over the code from Applications to ITI and make agreed improvements. 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2023 AMBER 40.0 days 57.0 days 10.0

Project Info

Project
Updates and Improvements to the AD and Exchange IDM Provisioners
Code
ENT405
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Graeme Wood
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
29-Nov-2021
Planning Date
18-Mar-2022
Delivery Date
23-Oct-2023
Close Date
06-Nov-2023
Programme Priority
3
Overall Priority
Higher
Category
Discretionary

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.