Current project status Report Date RAG Budget Effort Completed Effort to complete April 2024 BLUE 40.0 days 80.0 days 1.0 Content Status Closed Current Stage Close Start Date Monday, 29 November 2021 Planning Date Friday, 18 March 2022 Delivery Date Tuesday, 12 March 2024 Close Date Monday, 29 April 2024 Project information Project Code ENT405 Programme ITI - Enterprise Services (ENT) Session 23/24 22/23 21/22 Organisational Unit IS IT Infrastructure Project Management Office (if relevant) ISG PMO Responsibility IT Infrastructure Project Category Discretionary Project Classification Run Project Type Infrastructure Project Size Small Project Complexity Standard Alignment to Strategy 2030 and Adaptation & Renewal Team (ART) People Funding Source Core Programme Priority 3 Overall Priority Higher Student Impact Project deliverables will be used by students