Report for March 2023
- Report Date
- March 2024
Achievements this period
- Implementation successful
- Post-deployment issues resolved
- Closure review circulated for comments
- Closure milestone delayed due to absences
Risks and Issues
- Delivery identified that additional staff A5 licences will be needed going forward
Next Steps
- Close
Milestones
Closure: 29 April 2024
- Approved budget
- 40.0 days
- Activity this year
- 21.0 days
- Activity to date
- 79.0 days
- Estimate to complete current year
- 1.0 day
- Estimate to complete future years
- 0.0 days