The existing Sympa list service is now several revisions behind the current release. We will deploy a new version of Sympa on new virtual infrastructure and migrate the data to it. This will improve security, accessibility and functionality

Current project status

Report Date RAG Budget Effort Completed Effort to complete
November 2023 GREEN 100.0 days 11.0 days 89.0

Project Info

Project
Mailing list service upgrade
Code
ENT406
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Graeme Wood
Current Stage
Deliver
Status
In Progress
Project Classification
Run
Start Date
09-May-2022
Planning Date
26-May-2022
Delivery Date
01-Nov-2023
Close Date
19-Dec-2023
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.