Current project status Report Date RAG Budget Effort Completed Effort to complete May 2024 BLUE 50.0 days 4.0 days 50.0 Content Status Withdrawn Current Stage Close Start Date Monday, 12 February 2024 Planning Date Friday, 17 May 2024 Delivery Date Friday, 28 June 2024 Close Date Friday, 26 July 2024 Project information Project Code ENT601 Programme ITI - Enterprise Services (ENT) Session 23/24 Organisational Unit IS IT Infrastructure Project Management Office (if relevant) ISG PMO Responsibility IT Infrastructure Project Category Discretionary Project Classification Run Project Type Infrastructure Project Size Medium Project Complexity Simple Funding Source Core Overall Priority Normal