Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for Febuary 2025 February 2025 GREEN GREEN GREEN GREEN No Change
Report for January 2025 January 2025 GREEN GREEN GREEN GREEN No Change
Report for December 2024 December 2024 GREEN GREEN GREEN GREEN No Change
Report for November 2024 November 2024 GREEN GREEN GREEN GREEN No Change
Report for October 2024 October 2024 GREEN GREEN GREEN GREEN No Change

Project Info

Project
Improvements to MS365 Licence Management
Code
ENT701
Programme
ITI - Enterprise Services (ENT)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
09-Sep-2024
Planning Date
04-Nov-2024
Delivery Date
24-Feb-2025
Close Date
27-Mar-2025
Programme Priority
3
Overall Priority
Normal
Category
Discretionary

Documentation