Report for Febuary 2025
- Report Date
- February 2025
Achievements this period
- Student Ambassadors assigned A1 licence and ongoing reassignment agreed with stakeholders
- Invigilators identified for reassignment to A1 licence and ongoing reassignment agreed with stakeholders
- Business as usual process for future licence reassignments in development
Risks and Issues
Next steps
- Approve ongoing BAU process
- Close
Milestones
Close | 18-Mar-2025 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days