Q2 2019/2020

Report Date
February 2020

2019 Office Awards successfully delivered on time. 

18 teams participated in the Office Awards, with a further 11 teams remaining accredited from 2018. All teams successfully achieved their chosen award level - 9 Gold (7 projects), 6 Silver and 3 Bronze. This brings the total number of teams to 29. 

Audits were carried out in November by student volunteers, including those on the Climate Pathways programme. Students received a training session which included the chance to carry out a mock audit, and were able to gain valuable experience in sustainability auditing and report writing. The reports were provided to the teams in December along with confirmation of their award level. 

 

211 staff members actively participated in the 2019 Office Awards. This figure includes team members and champions from both awarded and still accredited teams. This equates to 1.36% of University staff. For both the Office and Lab Awards, the figures are 254 staff members participating equating to 1.63% of total University Staff. 

4,225 staff were reached by the 2019 Office Awards, including both awarded and still accredited teams. This equates to 27.19% of University staff. 

For both Lab and Office Awards, 5867 staff were reached, which is 37.73% of University staff. 51.05% of the student population was reached by the Office and Lab Awards.

Staff and students were asked to provide feedback on their experience taking part in the awards, and this was very positive. 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
ESA1 Office Awards
Code
ESA1
Programme
SRS - Edinburgh Sustainability Awards (ESA)
Project Manager
Rachael Barton
Project Sponsor
Michelle Brown
Current Stage
Deliver
Status
In Progress
Start Date
01-Aug-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Jul-2021
Overall Priority
Normal

Documentation

Not available.