Report for April 2013

Report Date
April 2013
  • Achievements in Last Period

A full install of Version 20, new 64-bit overlay, DWG and AutoCAD have been deployed using detailed instructions from MASS.

All fixes for Lease Module issues have passed testing and been deployed to LIVE.

Previous issues in IS APPS developed reports for space management have been resolved by revisiting the deployment.

  • Issues

DWG Viewer not functioning correctly after full re-install. MASS revisiting with Archibus support.

  • Next Steps

Outstanding issue on DWG to be resolved.

Arrange DSOR and Closure on successful testing of outstanding issues.

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
128.0 days
Activity this month
6.0 days
Activity this year
72.0 days
Activity to date
125.0 days
Estimate to complete current year
3.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Archibus Upgrade for Windows 7
Code
EST069
Programme
Z. Estates Systems & Technology Maintenance (EST) - Closed
Project Manager
Stephen Conlon
Project Sponsor
Geoffrey Turnbull
Current Stage
Close
Status
Closed
Start Date
01-Mar-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
12-Jun-2013
Category
Compliance