Report for April 2013
- Report Date
- April 2013
- Achievements in Last Period
A full install of Version 20, new 64-bit overlay, DWG and AutoCAD have been deployed using detailed instructions from MASS.
All fixes for Lease Module issues have passed testing and been deployed to LIVE.
Previous issues in IS APPS developed reports for space management have been resolved by revisiting the deployment.
- Issues
DWG Viewer not functioning correctly after full re-install. MASS revisiting with Archibus support.
- Next Steps
Outstanding issue on DWG to be resolved.
Arrange DSOR and Closure on successful testing of outstanding issues.
- Approved budget
- 128.0 days
- Activity this month
- 6.0 days
- Activity this year
- 72.0 days
- Activity to date
- 125.0 days
- Estimate to complete current year
- 3.0 days
- Estimate to complete future years
- 0.0 days