DSOR and Closure complete |
Items finished 4/06/13. - Alister and Ron Stopped updating TEST 10 am 4-Jun - Anne M Sent Anne F the Roles and Responsibilities document on project website - 4-Jun - Dougie gave Alister the 6 client pc details and Alister updated the wiki with them. One new client pc is due to be set up. - Georgina asked about the TAD diagram on 7-Feb-13 Georgina fed a comment back from the previous TAD EST054 that one supplier in 2008 didn't feel it was correct, however the EST072 diagram is for the 3 suppliers |
Anne Mathison | 04-Jun-2013 |
Scheduled Monthly windows o/s patching |
|
Anne Mathison | 22-May-2013 |
LIVE Built - switch over delayed 1 day |
Alister was planning to switch over EST072 metering today however neither Optima/Charlotte or E&B / Georgina are in. Alister had agreed this last week So will be carried out on the 7th. |
Anne Mathison | 06-May-2013 |
UAT testing progress is recorded in the UAT Signoff |
UAT testing progress is recorded in the UAT Signoff https://www.projects.ed.ac.uk/project/est072/milestones/acceptance
|
Anne Mathison | 22-Apr-2013 |
Acceptance teststing sign off delay |
Have to replan again as Optima contact who will verify testing with Estates is off sick and is suspected with Flu.
Testing may be able to proceed week beginning 8th April assuming required people are back, but will delay all later milestones milestones |
Anne Mathison | 18-Mar-2013 |
User Testing and Go Live plans |
Georgina plans to do User Testing on Monday 18th March for Energy Recording Systems. The only item Georgina feels might be tricky is to practice installing a new meter. These tend to arrive in batches, however she has none to do at present.
If we cannot install this work by 25th March we are likely to have to wait until the 17th April, given holidays of the project personnel
|
Anne Mathison | 13-Mar-2013 |
Build Test 80% complete |
Build Test 80% complete Alister looking into Lantronmix to see if MeterRing MM are still using it, Dynamat no longer use Lantronmix |
Anne Mathison | 04-Mar-2013 |
Build Test delayed by 1 week |
Build Test delayed by 1 week Alister working on another estates project this week, so cannot start build Test work yet. Milestones not changeing as the current dates may still be achievable |
Anne Mathison | 18-Feb-2013 |
TAD complete and sent out to stakeholders |
Sent out for PPDR meeting on the 12th Feb |
Anne Mathison | 05-Feb-2013 |
replan TAD to start 11th Feb - TAD started 29th Jan |
project will not deploy until 1st April
Now TAD out for review when comments back will replan the PPDR review
TAD sent to 3 suppliers and to Paul ITI Architecture I130131-0221 for review 31/01/13 |
Anne Mathison | 22-Jan-2013 |
EST072 TAD delay |
Won't be completed until later this week then have to get the suppliers to reveiw the TAD before the official signoff. Monday 21st Jan - Exchange down so will delay TAD progress. |
Anne Mathison | 21-Jan-2013 |
WIS Notes |
Approved new estimate 34 days |
Anne Mathison | 09-Jan-2013 |
Update |
Update 8/1/13 ITI items set up and TAD underway. TAD has been impacted by COM001 - Office 365. Pride has had to work on this on 7th and 8th, so has not had the resourced time he expected to have available for this work. Pride still expects to have the TAD completed by 21/22 Jan and have it reviewed and agreed by the external supliers by the 25th, so that Buld/Acceptance testing can proceed as expected. |
Anne Mathison | 08-Jan-2013 |
Brief approved at WIS 9/11/12 |
Brief approved at WIS 9/11/12 |
Anne Mathison | 12-Nov-2012 |
Likely cost of separate server - indication |
Asked Iain and Indicative cost £2,500 over 5 years |
Anne Mathison | 05-Nov-2012 |
Breakdown Notes of Initial Requirements |
Initial Requirements
|
Anne Mathison | 24-Oct-2012 |