Project journal

Title Description Author Post date
DSOR and Closure complete

Items finished 4/06/13.

- Alister and Ron Stopped updating TEST 10 am 4-Jun

- Anne M Sent Anne F the Roles and Responsibilities document on project website - 4-Jun

- Dougie gave Alister the 6 client pc details and Alister updated the wiki with them. One new client pc is due to be set up.

- Georgina asked about the TAD diagram on 7-Feb-13

Georgina fed a comment back from the previous TAD EST054 that one supplier in 2008 didn't feel it was correct, however the EST072 diagram is for the 3 suppliers

Anne Mathison 04-Jun-2013
Scheduled Monthly windows o/s patching

 

 

Anne Mathison 22-May-2013
LIVE Built - switch over delayed 1 day

Alister was planning to switch over EST072 metering today however neither Optima/Charlotte or E&B / Georgina are in.

Alister had agreed this last week

So will be carried out on the 7th.  

Anne Mathison 06-May-2013
UAT testing progress is recorded in the UAT Signoff

UAT testing progress is recorded in the UAT Signoff

https://www.projects.ed.ac.uk/project/est072/milestones/acceptance

 

 

Anne Mathison 22-Apr-2013
Acceptance teststing sign off delay

Have to replan again as Optima contact who will verify testing with Estates is off sick and is suspected with Flu.

 

Testing may be able to proceed week beginning 8th April assuming required people are back, but will delay all later milestones milestones

Anne Mathison 18-Mar-2013
User Testing and Go Live plans

Georgina plans to do User Testing on Monday 18th March for Energy Recording Systems.

 The only item Georgina feels might be tricky is to practice installing a new meter. These tend to arrive in batches, however she has none to do at present.

 

If we cannot install this work by 25th March we are likely to have to wait until the 17th April, given holidays of the project personnel

 

Anne Mathison 13-Mar-2013
Build Test 80% complete

Build Test 80% complete

Alister looking into Lantronmix to see if MeterRing MM are still using it, Dynamat no longer use Lantronmix

Anne Mathison 04-Mar-2013
Build Test delayed by 1 week

Build Test delayed by 1 week

Alister working on another estates project this week, so cannot start build Test work yet. Milestones not changeing as the current dates may still be achievable

Anne Mathison 18-Feb-2013
TAD complete and sent out to stakeholders

Sent out for PPDR meeting on the 12th Feb

Anne Mathison 05-Feb-2013
replan TAD to start 11th Feb - TAD started 29th Jan

project will not deploy until 1st April

 

Now TAD out for review when comments back will replan the PPDR review

 

TAD sent to 3 suppliers and to Paul ITI Architecture I130131-0221 for review 31/01/13

Anne Mathison 22-Jan-2013
EST072 TAD delay

Won't be completed until later this week then have to get the suppliers to reveiw the TAD before the official signoff.

Monday 21st Jan - Exchange down so will delay TAD progress.

Anne Mathison 21-Jan-2013
WIS Notes

Approved new estimate 34 days

Anne Mathison 09-Jan-2013
Update

Update 8/1/13

ITI items set up and TAD underway.

TAD has been impacted by COM001 - Office 365. Pride has had to work on this on 7th and 8th, so has not had the resourced time he expected to have available for this work.

Pride still expects to have the TAD completed by 21/22 Jan and have it reviewed and agreed by the external supliers by the 25th, so that Buld/Acceptance testing can proceed as expected.

Anne Mathison 08-Jan-2013
Brief approved at WIS 9/11/12

 

Brief approved at WIS 9/11/12

Anne Mathison 12-Nov-2012
Likely cost of separate server - indication

Asked Iain and Indicative cost £2,500 over 5 years

Anne Mathison 05-Nov-2012
Breakdown Notes of Initial Requirements

Initial Requirements

  • Audit of existing server
  • Confirm what has to be moved
  • Determine required infrastructure and costs, suspect infrastructure at KB and AT
  • Confirm proposed solution with supplier
  • Build new environment
  • Data migration and Test
  • Requirement to ascertain long term support
  • Establish links with Estates and Building external suppliers
Anne Mathison 24-Oct-2012

Project Info

Project
Energy Recording Systems Upgrade
Code
EST072
Programme
Z. Estates Systems & Technology Maintenance (EST) - Closed
Project Manager
Anne Mathison
Project Sponsor
Geoffrey Turnbull
Current Stage
Close
Status
Closed
Start Date
11-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Jun-2013
Programme Priority
5
Overall Priority
Normal
Category
Compliance