March Report by Anne Mathison

Report Date
March 2013

Report by Anne Mathison for March 2013

Achievements in Last Period

  • Build of Test environment 100% complete
  • Acceptance testing is currently one third of the way through. Tests have been completed regarding Dynamat and MeterRing
  • Progressing testing that the Meters provide the same information on the new environment

 

Issues

  • The majority of testing is via Optima and this is still to be completed during the first half of April.
  • Optima Testing was scheduled to complete in Mid March, however the Optima contact departed early on the  morning of the 18th March with flu. Due to this absence, the project has been delayed a month, this delay also includes different IS Apps and E&B holidays and so the project will now not deploy until  the start of May.

Next Steps

  • Complete Optima Testing and Acceptance Testing
  • Acceptance Testing planned to be complete
  • Deployment to LIVE 

 

Milestones

 

DateMilestone
17-Apr-2013Acceptance
01-May-2013Deploy
13-May-2013DSOR and Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
41.0 days
Activity this month
6.0 days
Activity this year
28.0 days
Activity to date
28.0 days
Estimate to complete current year
14.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Energy Recording Systems Upgrade
Code
EST072
Programme
Z. Estates Systems & Technology Maintenance (EST) - Closed
Project Manager
Anne Mathison
Project Sponsor
Geoffrey Turnbull
Current Stage
Close
Status
Closed
Start Date
11-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Jun-2013
Programme Priority
5
Overall Priority
Normal
Category
Compliance