March Report by Anne Mathison
- Report Date
- March 2013
Report by Anne Mathison for March 2013
Achievements in Last Period
- Build of Test environment 100% complete
- Acceptance testing is currently one third of the way through. Tests have been completed regarding Dynamat and MeterRing
- Progressing testing that the Meters provide the same information on the new environment
Issues
- The majority of testing is via Optima and this is still to be completed during the first half of April.
- Optima Testing was scheduled to complete in Mid March, however the Optima contact departed early on the morning of the 18th March with flu. Due to this absence, the project has been delayed a month, this delay also includes different IS Apps and E&B holidays and so the project will now not deploy until the start of May.
Next Steps
- Complete Optima Testing and Acceptance Testing
- Acceptance Testing planned to be complete
- Deployment to LIVE
Milestones
Date | Milestone |
17-Apr-2013 | Acceptance |
01-May-2013 | Deploy |
13-May-2013 | DSOR and Closure |
- Approved budget
- 41.0 days
- Activity this month
- 6.0 days
- Activity this year
- 28.0 days
- Activity to date
- 28.0 days
- Estimate to complete current year
- 14.0 days
- Estimate to complete future years
- 0.0 days