Monthly Progress Report
- Report Date
- April 2013
Report by Anne Mathison for April 2013
Achievements in Last Period
- Completed Acceptance Optima Testing
- Acceptance Testing completed
- Live VM Server Built
Issues
Next Steps
- Switchover to Live 7-May-13
- Deployment to LIVE 7-May-13 and Visible Optima Reports 8-May-13 both complete
- One run of monthly windows software updates
- Deployment Sign off and Closure
Milestones
06-May-2013 | Deploy |
20-May-2013 | DSOR and Closure |
- Approved budget
- 44.0 days
- Activity this month
- 10.0 days
- Activity this year
- 38.0 days
- Activity to date
- 38.0 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days