February 2013
- Report Date
- February 2013
Achievements in Last Period
- Two Webinars have been held between the project team and the PPM Trainer to get an understanding of the preparatory data to be captured
- A series of workshops have been held with members of the project team and representatives of the security team to review the preparatory date and categorise for the new system with regards
- Incidents
- Activities
- Roles
- Site
- An extract of the building data has been exported from EBIS to assist with the collation of site related data
- The Technical Architecture Document has been created and signed-off by the project team. In addition, the document has been reviewed and approved by a PPM 2000 Technical Support representative
- A site-visit by members of the project team to the University of Bristol has been undertaken with regards the implementation process
Issues
- None to report
Next Steps
- Complete the commission and the build of the new server infrastructure
- Sign-off the build phase
- Initial user training sessions have been arranged for 18th march and 2nd April
- Complete planning regarding training and configuration with PPM 2000 personnel
- Commence development of test script
- Approved budget
- 65.0 days
- Activity this month
- 6.3 days
- Activity this year
- 21.4 days
- Activity to date
- 21.4 days
- Estimate to complete current year
- 39.5 days
- Estimate to complete future years
- 0.0 days