Organisation
Work/Task Breakdown
- Produce Brief
- Produce and agree technical architecture document (TAD)
- Request required virtual servers
- Build TEST
- Configure specified alarm(s) on TEST
- Complete Acceptance Testing in TEST
- DR Testing will be done on the TEST environment as part of Acceptance testing to confirm the procedure works as it should
- prepare DR test script
- complete DR testing
- document DR procedures
- Build LIVE Server
- Configure LIVE and Migration data
- Complete Acceptance Testing in LIVE
- DR Testing will also be carried out on LIVE using the successful TEST plan
- Support LIVE until Closure
Resources Skills and Cost
For this project resources will required from the following areas
- IS Applications Project Services, Development Technology, Applications Management and Technology Management
- Estates and Buildings Energy Team
- External suppliers
- Trend - system owners
- East Coast Controls -
Project Estimate
82 days
2013-14
- 50 days
2014-15
- 32 days
Server Costs
- Server costs of £4,500 - £6,000 for 5 years will be incurred by Estates and Buildings
- To be confirmed during Design
- Costs upgrade Lite license to server license £3,500
- Alarm re-addressing
- Current license for 3 concurrent users, now require 6 concurrent users
- East Coast Controls for alarm re-addressing £960 for
- Roslin & Bush Estate
- Western General Hospital
- KB Biochar
- Pollock Halls – John MacIntyre Centre
- Pollock Halls – John Burnett House