Project Status Reports

Title Report Date Time Cost Scope Overall Change
Monthly Project Report November 2014 BLUE
Monthly Progess Report October 2014 BLUE
Monthly Progress Report September 2014 GREEN
Monthly Progress August 2014 GREEN
Monthly Progress Report July 2014 GREEN
Monthly Progress Report June 2014 AMBER
Progress Report May 2014 AMBER
Monthly Project Report April 2014 AMBER

Project Info

Project
Trend 963 Supervisor Server Migration (BEMS)
Code
EST079
Programme
Z. Estates Systems & Technology Maintenance (EST) - Closed
Project Manager
Anne Mathison
Project Sponsor
Dougie Williams
Current Stage
Close
Status
Closed
Start Date
05-May-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
25-Nov-2014
Category
Compliance