Monthly Progess Report

Report Date
October 2014

Achievements

  • Trend 963 Delivered (6-Oct)
  • Draft Closure Report produced

Issues

  • Issue raised with Windows monthly updates 16-Oct, revised milestone approved for 21-Nov at WIS 31-Oct.

Next Steps

  • Ensure Windows monthly updates do not result in Trend 963 server requiring a restart  
  • Agree Deployment Signoff and Closure
  • Project Complete

Milestones

New DateMilestone
20-Nov-2014Deployment Sign Off and Closure

 

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
55.0 days
Activity this month
4.9 days
Activity this year
29.4 days
Activity to date
55.8 days
Estimate to complete current year
2.4 days
Estimate to complete future years
0.0 days

Project Info

Project
Trend 963 Supervisor Server Migration (BEMS)
Code
EST079
Programme
Z. Estates Systems & Technology Maintenance (EST) - Closed
Project Manager
Anne Mathison
Project Sponsor
Dougie Williams
Current Stage
Close
Status
Closed
Start Date
05-May-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
25-Nov-2014
Category
Compliance