Monthly Progess Report
- Report Date
- October 2014
Achievements
- Trend 963 Delivered (6-Oct)
- Draft Closure Report produced
Issues
- Issue raised with Windows monthly updates 16-Oct, revised milestone approved for 21-Nov at WIS 31-Oct.
Next Steps
- Ensure Windows monthly updates do not result in Trend 963 server requiring a restart
- Agree Deployment Signoff and Closure
- Project Complete
Milestones
New Date | Milestone |
20-Nov-2014 | Deployment Sign Off and Closure |
- Approved budget
- 55.0 days
- Activity this month
- 4.9 days
- Activity this year
- 29.4 days
- Activity to date
- 55.8 days
- Estimate to complete current year
- 2.4 days
- Estimate to complete future years
- 0.0 days