Monthly Progress Report

Report Date
September 2014

 

During the month good progress has been made resulting in the system becoming operational on the new infrastructure

Achievements

  • The build of the LIVE environment was successfully completed  as a result of the following activity

    • Confirmed Live Acceptance

    • Planned DR LIVE
    • Completed DR test in LIVE
  • As a result of teh good progress, the budget set aside for contingency is no longer required and as a result, this has been reduced by 27 days from 82 to 55 days

Issues

  • Requirement to identify remote access connectivity for East Coast systems out of normal office hours

Next Steps

Complete the remaining stages regarding moving the project to completion, namely;

  • Deployment Sign Off
  • Closure

As the project continues according to plan, the project retain the RAG status of Green

Milestones

New DateMilestone
7-Oct-2014Deliver
21-Oct-2014Deployment Sign Off and Closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
55.0 days
Activity this month
13.0 days
Activity this year
24.0 days
Activity to date
50.0 days
Estimate to complete current year
4.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Trend 963 Supervisor Server Migration (BEMS)
Code
EST079
Programme
Z. Estates Systems & Technology Maintenance (EST) - Closed
Project Manager
Anne Mathison
Project Sponsor
Dougie Williams
Current Stage
Close
Status
Closed
Start Date
05-May-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
25-Nov-2014
Category
Compliance