Monthly Progress Report
- Report Date
- September 2014
During the month good progress has been made resulting in the system becoming operational on the new infrastructure
Achievements
The build of the LIVE environment was successfully completed as a result of the following activity
Confirmed Live Acceptance
- Planned DR LIVE
- Completed DR test in LIVE
- As a result of teh good progress, the budget set aside for contingency is no longer required and as a result, this has been reduced by 27 days from 82 to 55 days
Issues
- Requirement to identify remote access connectivity for East Coast systems out of normal office hours
Next Steps
Complete the remaining stages regarding moving the project to completion, namely;
- Deployment Sign Off
- Closure
As the project continues according to plan, the project retain the RAG status of Green
Milestones
New Date | Milestone |
7-Oct-2014 | Deliver |
21-Oct-2014 | Deployment Sign Off and Closure |
- Approved budget
- 55.0 days
- Activity this month
- 13.0 days
- Activity this year
- 24.0 days
- Activity to date
- 50.0 days
- Estimate to complete current year
- 4.0 days
- Estimate to complete future years
- 0.0 days