Monthly Report
- Report Date
- March 2016
Achievements:
- Three demonstration meetings took place to involve the EDMs and PPMs for EST084 (between 7-11 Mar)
- A permission overview meeting took place to ensure Estates understood and learnt how to set up and update SharePoint Estates Project permissions (4-Mar)
- Documentation, was along with the permissions meeting, will continue to be completed into April
- Progress meeting held with key stakeholders to agree end of pilot and who will sign off the stages (29-Mar)
Issue
- None
Next Steps:
- Documentation to be updated and completed
- Follow through agreements from 29-Mar meeting
- Review progress of EDM and PMs weekly
- Concern if no progress has been made
- Draft Closure report
- Complete project
Due to agreement of the milestones, this project has been assigned a GREEN RAG status
Milestones:
25-Apr-2016 | Proof of Concept and Pilot Conclusions |
29-Apr-2016 | Closure |
- Approved budget
- 120.0 days
- Activity this month
- 7.0 days
- Activity this year
- 52.0 days
- Activity to date
- 112.0 days
- Estimate to complete current year
- 7.0 days
- Estimate to complete future years
- 0.0 days