Report for Sept 2016
- Report Date
- September 2016
Achievements in Last Period
- Business analysis: Space Mgmt complete and signed-off.
- Business analysis: Maintenance Mgmt complete and signed-off.
Issues
- No project sponsor yet in place. There has been a lack on impetus in moving this project onto the next stage. Following recent discussions with Estates, it looks likely a sponsor will be appointed to give the project the direction required. A meeting will be arrange to discuss this.
- Project is dependent upon the outputs of-outcomes from project COM025 (BI/MI architecture), and the emerging project COM029 (EDW build). Details of the inter dependencies are emerging.
- The technical and development skills required for the project have been identified as a critical success factor. Discussions are on-going with the head of development services.
- Milestones to be adjusted, due to the delays in the appointment of a sponsor.
- PM Resource constraint with EST080, leading to additional delays.
Next Steps
- Confirm appointment of Sponsor.
- Re-boot project, Re-align project milestones.
- Plan design, development phases
- Commence design
The project is continue to report RED until such time as a sponsor is officially appointed.
- Approved budget
- 200.0 days
- Activity this month
- 0.7 days
- Activity this year
- 11.4 days
- Activity to date
- 50.6 days
- Estimate to complete current year
- 152.7 days
- Estimate to complete future years
- 0.0 days