Organisation
Work/Task Breakdown
- Project Planning Phase
- Complete project brief
- Sign-off project planning phase
- Project design Phase
- Update Technical Architecture Document
- Sign-off design
- Dynamat DATA BIRD Radio System Upgrade
- Prepare Test Plan for Dynamat DATA BIRD Radio System upgrade
- Procure and replace electric and heat meters for specified building
- Complete upgrade on Test environment
- Complete User Acceptance Testing
- Prepare Deployment Check List with regards upgrade
- Update Dynamat DATA BIRD Radio System on the Live environment
- Complete Deployment Sign-Off
- Dynamat 2050 Modbus System (Cloud Based)
- Install Dynamat 2050 Modbus System application
- Configure Dynamat 2050 Modbus System
- Configure specified meters to Dynamat 2050 Modbus System
- Prepare Test Plan
- Complete User Acceptance Testing
- Prepare Deployment Check List
- Complete Deployment Sign-off
- Optima Visualier
- Identify user training requirements
- Identify required reports to be prepared
- Complete user training
- Complete Optima visualier configuration
- Prepare and test reports
- Complete reports
- Project Closure
- Prepare project closure report
- Close project
Resources, Skills and Costs
This project will require representatives from the following departments;
Estates Energy Controls Department - Energy controller(s) to assist with Dynamat DATA BIRD Radio System and DATA BIRD Modbus System (Cloud Based) evaluation
Estates Energy Team -Energy team representatives to assist with Optima Visualiser
Project Services - Project Manager
IS Apps Development Technology - Technical lead
IS Apps Production Management - Applications and Technical representatives
The project has been estimated at 45 days
Project Governance
The project will be overseen by the project team with oversight by the project sponsor