w/c 8th May 2017
Project Team meeting held on Thursday 11th May
Dynamat
- Upgrade and Recovery of Missing Data
- On-going discussions with Estates, IS Apps and supplier regarding possible dates within May. Technical lead has advised that he will be not be available until 31st May
- The supplier has advised they could also provide a solution via a cloud based solution. After discussion with the project team, it was agreed that this could be further explored to determine the pros and cons
- On-going discussions regarding training to determine possible date
- Doodle poll set up to determine possible training dates
- In reviewing dates over the next two weeks, the only date acceptable to all (16th May) was not available to the supplier
- Further poll set up to extend dates to 13th June
- Doodle poll set up to determine possible training dates
- Project team have provided feedback regarding outline training schedule
- Holyrood metering review scheduled for Monday 22nd May by Robert MacGregor