w/c 11th September 2017

  • Risk Log 
    • current risk log reviewed and updated 
    • additional risk added - Risk 6: SQL Server 2014 Compatibility Issues 
  • Project Estimation 
    • Review of and update project estimate regarding remaining technical requirements 
  • Project Plan 
    • Review and update of current project plan 
    • ASTA updated to represent the revised plan and estimate 
  • Energy Metering Technology representatives on-site this week regarding
    • review of data issues and spreadsheet updated 
    • determine the most effective method of upload 
      • noting there is  months of data to upload 
      • first two weeks took around 24 hours to upload 
    • training course for the Energy and the Controls teams 
  • Meetings
    • Project meeting with business users scheduled for this week 
    • Project meeting with technical team scheduled this week 
  • Project Budget 
    • As of w/c 11th September, the project budget stated
      • Approved budget - 45 days 
      • Planned activity - 47.96 days
      • Effort to-date - 32 days 
      • Estimated effort to complete - 15.4 days 

Project Info

Project
Energy Systems Upgrade
Code
EST095
Programme
Z. Estates Systems & Technology Maintenance (EST) - Closed
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Grant Ferguson
Current Stage
Close
Status
Closed
Start Date
28-Nov-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Oct-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary