- Risk Log
- current risk log reviewed and updated
- additional risk added - Risk 6: SQL Server 2014 Compatibility Issues
- Project Estimation
- Review of and update project estimate regarding remaining technical requirements
- Project Plan
- Review and update of current project plan
- ASTA updated to represent the revised plan and estimate
- Energy Metering Technology representatives on-site this week regarding
- review of data issues and spreadsheet updated
- determine the most effective method of upload
- noting there is months of data to upload
- first two weeks took around 24 hours to upload
- training course for the Energy and the Controls teams
- Meetings
- Project meeting with business users scheduled for this week
- Project meeting with technical team scheduled this week
- Project Budget
- As of w/c 11th September, the project budget stated
- Approved budget - 45 days
- Planned activity - 47.96 days
- Effort to-date - 32 days
- Estimated effort to complete - 15.4 days