w/c 18th September 2017

  • Project Risk Log
    • Closed risk 5 - Impact on project plan - as new pilot meter has been installed and configured
    • Added additional risk 7- Project Plan impacted by delay in uploading missing data
  • Project updates 
    • project updated currently been sought from David Jack and Brian Eelbeck
  • Project meeting 
    • meeting with project team on 19/09/17
  • Project Plan 
    • Project plan updated after team meeting to allow for additional time to complete 
      • Optima Visualiser reporting 
      • Review of Dynamat Modbus pilot 
  • Missing data 
    • Spreadsheet updated and returned for Estates to review
  • Modbus Pilot Project 
    • Details to access cloud based solution received from the supplier and forwarded to the project team 

Project Info

Project
Energy Systems Upgrade
Code
EST095
Programme
Z. Estates Systems & Technology Maintenance (EST) - Closed
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Grant Ferguson
Current Stage
Close
Status
Closed
Start Date
28-Nov-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Oct-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary