- Circulated the following draft documentation to the project team for review
- Project brief
- Project plan
- Project estimate with regards IS Applications resources
- Project Risks
- Project Stakeholders
- Meeting scheduled for 27th January required to be rescheduled due to
- Project manager involvement with HelpDesk rollout support
- Lack of time for the Estates Energy and Controls teams due to other business priorities
- Meeting now rescheduled for 30th January
- Further request for IS Applications project representatives sent to Resource Managers