- Project Brief amended to
- Amend product name of Dynamat Cloud solution
- Incorporate additional dependency of Premises teams to arrange building shutdown
- Confirmation of building to used in the Dynamat Cloud pilot
- Incorporated procurement requirement for replacement meters for the pilot building
- Extended project elapsed time by 4 weeks to accommodate meters procurement
- Business Lead confirmed project brief sign-off on behalf of the project sponsor
- Project brief submitted to WIS