Report for September 2017
- Report Date
- September 2017
Achievements in Last Period
- Dynamat RadioBird - Live
- A sample amount of data (two weeks) has been imported but the process to clear the anomalies is still being worked though by the Controls team and the supplier
- Dynamat DATA BIRD Modbus 2050 TEST
- The scheduled product workshop was held on 15th September
- New meter data is being recorded
- Project team have now access to review the cloud based pilot project
- Optima Visualiser
- Remaining reporting workshop is now being planned
- Project Governance
- As a result of the change of project manager
- The project has been re-planned and re-estimated
- The risk log has been reviewed and updated
- Clarification was sought regarding the future direction of this project from the project sponsor and programme manager with regards to the options noted below. The feedback via the programme manager was to minimise the changes until the Energy Systems review is completed and so maintain the current plan
- Maintain current project plan
- import of missing data
- upgrade to Dynamat Radio Bird
- review of Dynamat cloud based solution
- Review Dynamat cloud based solution and if proves to be fit for purpose
- move to the cloud based solution
- import of missing data would not be required
- upgrade of Dynamat Radio Bird would not be required
- Maintain current project plan
Issues
- Having re-planned and re-estimated the project, there will be the requirement to extend the project milestones and increase the project budget.
- Progress has being hampered due holidays and office move preparations
Next Steps
- Dynamat RadioBird - Live
- Import the rest of the missing data
- Dynamat RadioBird - Test
- Commence upgrade of current Radio Bird system on Test
- Commence user acceptance testing
- Dynamat DATA BIRD Modbus Upgrade
- Continue to review cloud based solution
- complete user acceptance testing
- Optima Visualiser
- schedule remaining reporting workshop
As a result of the proposed delivery milestones being extended by more than one month and the budget increasing by more than 10%, the project RAG status for this month is Red
- Approved budget
- 45.0 days
- Activity this month
- 7.0 days
- Activity this year
- 15.7 days
- Activity to date
- 41.4 days
- Estimate to complete current year
- 14.9 days
- Estimate to complete future years
- 0.0 days