Report for March 2017
- Report Date
- March 2017
Achievements in Last Period
- Work has commenced on the update of the Technical Architecture Document (TAD)
- Resolved data connectivity connection between Dynamat and Optima
Issues
- Work on the Technical Architecture Document (TAD) has been delayed due to the technical lead being also assigned to the EST080 HelpDesk project
- No progress in clarifying dates with third party supplier to undertake system update and pilot implementation
- having re-established the data connectivity issue between Dynamat and Optima, there is the requirement to re-apply the missing data
Next Steps
- Complete the design phase of the project
- Confirm dates with third party supplier to undertake system update and pilot implementation
- Determine the way forward regarding the process to re-apply the missing data
- Approved budget
- 45.0 days
- Activity this month
- 4.0 days
- Activity this year
- 11.0 days
- Activity to date
- 11.0 days
- Estimate to complete current year
- 35.0 days
- Estimate to complete future years
- 0.0 days