Report for April 2017

Report Date
April 2017

Achievements in Last Period

  • The┬áTechnical Architecture Document (TAD)┬áhas been completed
  • A strategy regarding repairing the missing data in Dynamt has been agreed and planning is now underway
  • Dates for Optima Resolver workshop confirmed for early June

Issues

  • None

Next Steps

  • Complete the design phase of the project by signing of the TAD
  • Confirm dates with third party supplier to undertake system update and pilot implementation
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Change: Project scope change to enable data correction process to be undertaken.
Change Status
Activity
Approved budget
45.0 days
Activity this month
4.0 days
Activity this year
16.0 days
Activity to date
16.0 days
Estimate to complete current year
37.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Energy Systems Upgrade
Code
EST095
Programme
Estates Systems & Technology Maintenance (EST)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Grant Ferguson
Current Stage
Close
Status
Closed
Start Date
28-Nov-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Oct-2017
Programme Priority
2
Overall Priority
Normal
Category