Report for May 2017
- Report Date
- May 2017
Achievements in Last Period
- The Technical Architecture Document (TAD) has been completed
- A strategy regarding repairing the missing data in Dynamt has been agreed and planning is now underway
- Dates for Optima Resolver workshop confirmed for early June
Issues
- Requirement to re-plan Dynamat related project activities due to lack of resource both within IS Applications and Estates
Next Steps
- Complete re-planning exercise
- Commence Dynamat upgrade
- Arrange Dynamat related training
- Approved budget
- 45.0 days
- Activity this month
- 2.0 days
- Activity this year
- 19.0 days
- Activity to date
- 19.0 days
- Estimate to complete current year
- 12.0 days
- Estimate to complete future years
- 13.0 days