Report for June 2017
- Report Date
- June 2017
Achievements in Last Period
- Complete re-planning exercise
- Commence Dynamat upgrade
- Arrange Dynamat related training
Issues
- Requirement to re-plan Dynamat related project activities due to lack of resource both within IS Applications and Estates
Next Steps
- Restore Dynamat Data
- Conplete Dynamat upgtrade
- Complete Dynamat related training
- Approved budget
- 45.0 days
- Activity this month
- 1.8 days
- Activity this year
- 22.1 days
- Activity to date
- 22.1 days
- Estimate to complete current year
- 11.4 days
- Estimate to complete future years
- 13.4 days