Report for August 2017

Report Date
August 2017

Achievements in Last Period

  • A sample amount of data has been imported and is undergoing UAT.
  • Dynamat DATA BIRD Modbus 2050 TEST
    • The electrical point has been installed.
    • A heat meter point has been installed.
    • Dynamat has been contacted to install the new meter.
  • Optima Visualiser has been installed.

Issues

  • Requirement to re-plan Dynamat related project activities due to lack of resource both within IS Applications and Estates

Next Steps

  • Restore the rest of the missing data.
  • Dynamat will supply training on the new system.
  • Dynamat DATA BIRD Modbus Upgrade
    • Dynamat to complete the installation of the new meter.
    • Implement test environment.
    • Complete UAT
Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
45.0 days
Activity this month
3.4 days
Activity this year
3.4 days
Activity to date
29.1 days
Estimate to complete current year
25.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Energy Systems Upgrade
Code
EST095
Programme
Estates Systems & Technology Maintenance (EST)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Grant Ferguson
Current Stage
Close
Status
Closed
Start Date
28-Nov-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Oct-2017
Programme Priority
2
Overall Priority
Normal
Category
Discretionary