w/c 17th July 2017

  • Continued work on project brief encompassing
    • Update to work breakdown tasks
    • Updated project stakeholder maps for project board and team
    • Updated project plan
    • commenced project resourcing for business team members
  • Business Analysis
    • Initial discussions held with Estates Development finance representative

Project Info

Project
Estates Purchase To Payment
Code
EST097
Programme
Estates Business Operations Optimisation Programme (EOO)
Management Office
ISG PMO
Project Manager
Helen Lobb
Project Sponsor
Karen Adamson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Jan-2017
Planning Date
28-Feb-2019
Delivery Date
31-Jul-2019
Close Date
16-Aug-2019
Programme Priority
2
Overall Priority
Normal
Category
Discretionary