Report for May 2017

Report Date
May 2017

Achievements in Last Period

  • A new Business Analyst  has now commenced
  • Business Analysis
    • Review of current AS-IS documentation
    • Commenced review of current AS-IS current processes 
    • Initial meetings held with EBIS Office, Procurement and Estates Finance

Issues

  • It has not been possible to progress with the project brief due to lack of availability of the  project manager due to other Estates projects and also other activities associated with Accommodation Catering and Events. As a result the planning phase milestone has been extended to the middle of June
  • The project team has still to be confirmed
  • Representatives of Estates Finance have expressed initial concerns regarding their availability due to holidays and financial year end
  • Due the delays it is now anticipated that the planned activity of will be reduced to 63 days this year

Next Steps

  • Continue the project planning phase with a view to
    • preparation of an outline project plan and estimate
    • confirmation of the members for both the project board and project team
  • Commence the project risk register
  • Commence project management strategy
  • Commence Change and Communications strategies
  • Continue business analysis with specific subject matter experts

 

The project has been assigned a Red rag status due to lack of progress.

Project Status
RAG Status
Time
RED
Cost
RED
Scope
GREEN
Overall
RED
RAG Commentary
Issue: Project brief delayed due to time project manager assigning to close of EST008 Estates Helpdesk project, delay in the appointment of a business analyst and concerns regarding Estates resourcing
Change Status
Activity
Approved budget
63.0 days
Activity this month
3.0 days
Activity this year
18.0 days
Activity to date
18.0 days
Estimate to complete current year
41.0 days
Estimate to complete future years
280.0 days

Project Info

Project
Estates Purchase To Payment
Code
EST097
Programme
Estates Business Operations Optimisation Programme (EOO)
Management Office
ISG PMO
Project Manager
Helen Lobb
Project Sponsor
Karen Adamson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
20-Jan-2017
Planning Date
28-Feb-2019
Delivery Date
31-Jul-2019
Close Date
16-Aug-2019
Programme Priority
2
Overall Priority
Normal
Category
Discretionary