Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for November 2018 November 2018 GREEN GREEN GREEN GREEN Within Tolerance
Report for October 2018 October 2018 AMBER AMBER AMBER GREEN Within Tolerance
Report for August 2018 August 2018 AMBER GREEN GREEN GREEN
Report for July 2018 July 2018 GREEN GREEN GREEN GREEN
Report for June 2018 June 2018 AMBER AMBER GREEN AMBER
Report for May 2018 May 2018 RED RED GREEN AMBER
Report for April 2018 April 2018 AMBER AMBER GREEN AMBER
Report for March 2018 March 2018 AMBER GREEN GREEN AMBER
Report for February 2018 February 2018 AMBER GREEN GREEN AMBER
Report for January 2018 January 2018 AMBER GREEN GREEN AMBER
Report for November 2017 November 2017 AMBER AMBER GREEN AMBER
Report for October 2017 October 2017 RED GREEN GREEN RED
Report for September 2017 September 2017 GREEN GREEN GREEN GREEN
Report for August 2017 August 2017 GREEN GREEN GREEN GREEN
Report for June 2017 June 2017 AMBER GREEN GREEN AMBER
Report for May 2017 May 2017 GREEN GREEN GREEN GREEN

Project Info

Project
Asset Management
Code
EST099
Programme
Estates Business Operations Optimisation Programme (EOO)
Management Office
ISG PMO
Project Manager
Helen Lobb
Project Sponsor
Grant Ferguson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
24-Jul-2017
Planning Date
13-Jul-2018
Delivery Date
09-May-2019
Close Date
19-Jul-2019
Programme Priority
2
Overall Priority
Normal
Category
Discretionary