Report for November 2017

Report Date
November 2017

Achievements in Last Period

•Asset Data Capture using mobile devices completed the survey of the 56 buildings.

•Project Brief

  • Accepted by MASS
  • Not approved at WIS

•Project Planning

  • Refined to take account of EST098 dependency
  • Accepted by MASS

•Migration approach agreed (utilise ARCHIBUS 23.1 test environment)

Issues

•Technical resource capacity and prioritisation issue from internal Dev Tech allocated resource and 3rd party team MASS have been an issue while the ARCHIBUS Upgrade project EST098 takes priority; Alleviated by the delay to EST099 delivery

•Resource forecast to be revalidated/approved based on

  • Re-planning activity
  • Brought into line with original 3 point estimate

•Project Brief not accepted by WIS; Rework ongoing

Next Steps

•Next Project Board to be scheduled

•Resource estimate to be formally accepted by Estates

•Asta to be refined with resource estimates

•Project Brief to be resubmitted to WIS

•Test Plan and Test Script

•Create Test Environment for initial Transmission and Reconciliation of data.

 

 

Project status Amber, due to outstanding formal approval of the request for additional budget from Estates.

Project Status
RAG Status
Time
AMBER
Cost
AMBER
Scope
GREEN
Overall
AMBER
RAG Commentary
ISSUE : Revised project estimate submitted for Estates approval. Project Brief cannot be fully signed off until the funded budget has been agreed. No SMT action requested.
Change Status
Activity
Approved budget
50.0 days
Activity this month
12.0 days
Activity this year
61.0 days
Activity to date
71.0 days
Estimate to complete current year
5.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Asset Management
Code
EST099
Programme
Estates Business Operations Optimisation Programme (EOO)
Management Office
ISG PMO
Project Manager
Helen Lobb
Project Sponsor
Grant Ferguson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
24-Jul-2017
Planning Date
13-Jul-2018
Delivery Date
09-May-2019
Close Date
19-Jul-2019
Programme Priority
2
Overall Priority
Normal
Category
Discretionary