Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for October 2018 October 2018 GREEN GREEN GREEN GREEN
Report for September 2018 September 2018 GREEN GREEN GREEN GREEN
Report for August 2018 August 2018 GREEN GREEN GREEN GREEN
Report for July 2018 July 2018 GREEN GREEN GREEN GREEN
Report for June 2018 June 2018 GREEN GREEN GREEN GREEN
Report for May 2018 May 2018 GREEN GREEN GREEN GREEN
Report for April 2018 April 2018 AMBER GREEN GREEN GREEN
Report for March 2018 March 2018 AMBER GREEN GREEN GREEN
Report for February 2018 February 2018 AMBER GREEN GREEN GREEN
Report for January 2018 January 2018 GREEN GREEN GREEN GREEN
Report for December 2017 December 2017 RED GREEN GREEN RED
Report for November 2017 November 2017 RED GREEN RED RED
Report for October 2017 October 2017 RED GREEN RED RED
GREEN: Estates EPPM Procurement proceeding on target September 2017 GREEN
GREEN: Estates EPPM Procurement proceeding on target August 2017 GREEN
Report for July July 2017 AMBER GREEN GREEN GREEN
2 x risks raised due to loss of Procurement specialist on 14th July. Invitation to Tender likely to be delayed with impact on EST102 timescales June 2017 AMBER AMBER
Report for April 2017 April 2017 GREEN
Report for February 2017 February 2017 GREEN

Project Info

Project
Estates Capital System Procurement (EST102)
Code
EST102
Programme
Z. Estates Capital System (ECS) - CLOSED
Management Office
ISG PMO
Project Manager
Lyn Thomson
Project Sponsor
Anna Stamp
Current Stage
Close
Status
Closed
Start Date
04-Nov-2016
Planning Date
31-May-2017
Delivery Date
25-May-2018
Close Date
22-Jun-2018
Programme Priority
1
Overall Priority
Higher
Category
Discretionary