Report for October 2018

Report Date
October 2018

Achievements

  • Review of project close report from Mark Ritchie

 

Next Steps:

  • Resubmission for closure to WIS 9th November

 

 

Issues:

None.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
218.0 days
Activity this month
0.2 days
Activity this year
1.2 days
Activity to date
243.2 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Estates Capital System Procurement (EST102)
Code
EST102
Programme
Z. Estates Capital System (ECS) - CLOSED
Management Office
ISG PMO
Project Manager
Lyn Thomson
Project Sponsor
Anna Stamp
Current Stage
Close
Status
Closed
Start Date
04-Nov-2016
Planning Date
31-May-2017
Delivery Date
25-May-2018
Close Date
22-Jun-2018
Programme Priority
1
Overall Priority
Higher
Category
Discretionary

Documentation