Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2020 GREEN 514.0 days 575.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Tuesday, 13 June 2017
Planning Date
Thursday, 15 November 2018
Delivery Date
Thursday, 13 June 2019
Close Date
Friday, 31 July 2020
Project information
Project Code
EST103
Programme
Estates Systems & Technology Maintenance (EST)
Session
19/20
18/19
17/18
16/17
Organisational Unit
Estates Department
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Discretionary
Project Classification
Transform
Funding Source
Estates
Programme Priority
2
Overall Priority
Highest