Report for March 2018

Report Date
March 2018

Achievements

  • 7th March:  Formal engagement meeting with IS Section Heads.
  • 19th March:  Lunchtime Seminar delivered to audience of 30 drawn from around the University.
  • Communications Plan Complete

 

Next Steps

  • 16th April 2018:  Refine resource calculation with IS section heads and enter formal resource requests in ASTA.
  • Project Audit: Approach Andy Stewart to ask him to audit.
  • 25th April 2018:  Early Planning Session with Polarisoft.  Polarisoft  will take 6 weeks to mobilise after signing the contract.  In order to mitigate the effect of this we will have planning sessions during the 6 weeks so that we start Design and Build as early as possible.

 

Issues

Slow progress towards the signing of the final contract is delaying the start of EST103.  Every effort is being made to carry out activities that will allow a speedy start once this is achieved.  Polarisoft will participate in an early planning meeting ahead of the final award of contract to assist us.

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
AMBER
RAG Commentary
The status of the project will remain amber until further joint planning activities are completed and we have clarity around the timeline and resource requirement.
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Estates EPPM Implementation
Code
EST103
Programme
Z. Estates Systems & Technology Maintenance (EST) - Closed
Management Office
ISG PMO
Project Manager
Derrick Matheson
Project Sponsor
Jane Johnston
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
13-Jun-2017
Planning Date
15-Nov-2018
Delivery Date
13-Jun-2019
Close Date
31-Jul-2020
Programme Priority
2
Overall Priority
Highest
Category
Discretionary