Project to provide a recommendation for a digital automated system to support the capture, management and reporting  of Fire Safety Incidents  handled by Corporate Services Group H&S team.

 

EST108 project closed.  CSG013 has been opened within CSG portfolio.

 

PICCL Raised: Commentary is:

EST108 opened as placeholder to align with EST107 requirements.  Agreement made with CSG portfolio manager to initiate CSG013 to capture activity within the correct portfolio.  EST108 closed.

Programme managers to meet in order to ensure no gaps between projects.  CSG PM to schedule

Update 17th November after meeting Mark Ritchie and Nikki Stuart - agreed to withdraw rather than close, with time transferred to CSG013

Current project status

Report Date RAG Budget Effort Completed Effort to complete
October 2017 BLUE 0.0 days 0.0 days 0.0

Project Info

Project
Corporate Services Group Health & Safety - Fire Safety System
Code
EST108
Programme
Estates Systems & Technology Maintenance (EST)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
ALASTAIR Reid
Current Stage
Close
Status
Withdrawn
Start Date
01-Aug-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal
Category
Discretionary

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.