Report for June 2018
- Report Date
- June 2018
Achievements in Last Period
- ETL Build in progress.
Issues
- Development running approx. 3 weeks behind schedule. Governance update is in progress.
- Definition of support arrangements for reports. Meeting organised for August.
Next Steps
- Continue ETL build.
The project is reporting AMBER, given likelihood of further slippage.
- Approved budget
- 282.0 days
- Activity this month
- 21.4 days
- Activity this year
- 172.4 days
- Activity to date
- 172.4 days
- Estimate to complete current year
- 21.3 days
- Estimate to complete future years
- 104.2 days