Report for December 2018
- Report Date
- December 2018
Achievements in Last Period
- Maintenance reports in progress.
- UAT planning in progress.
- Change to Milestones / Budget approved though governance.
Issues
- Late delivery of Maintenance reports, due to change of development resource.
- Some last minute ETL flow changes due to data quality issues discovered during integration testing.
- Potential for resource contention on key Dev Tech resource: situation to be monitored.
- PM is leaving UofE 31/1/2019. Replacement PM required for Feb / Mar.
Next Steps
- Complete Maintenance Report build. Move to TEST.
- Start UAT
The project is reporting GREEN.
- Approved budget
- 349.0 days
- Activity this month
- 13.4 days
- Activity this year
- 123.2 days
- Activity to date
- 313.1 days
- Estimate to complete current year
- 46.8 days
- Estimate to complete future years
- 0.0 days