Report for March 2019

Report Date
March 2019

Awaiting timescale for reports in order to begin UAT.  Meetings held with Service Management and Architecture teams to confirm delivery dates for reports.  Due to lack of attendance at last client meeting, another meeting has been scheduled in April to confirm report scope for remaining reports.

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
349.0 days
Activity this month
10.0 days
Activity this year
359.0 days
Activity to date
359.0 days
Estimate to complete current year
33.6 days
Estimate to complete future years
0.0 days

Project Info

Project
Estates Strategic Reporting - Space & Maintenance Mgmt
Code
EST109
Programme
Estates Systems & Technology Maintenance (EST)
Management Office
ISG PMO
Project Manager
Josephine McDonald
Project Sponsor
Karen Adamson
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
02-Oct-2017
Planning Date
06-Oct-2017
Delivery Date
26-Jun-2020
Close Date
31-Jul-2020
Programme Priority
3
Overall Priority
Higher
Category
Discretionary