Report for February 2018
- Report Date
- February 2018
Achievements in Last Period
- Business Analysis signed off.
- Design phase in progress.
Issues
- Design phase is running late, approx. 1 week.
- Key business SME has limited time to devote to the project, due to unavoidable constraints.
- Project is dependent upon the delivery of EDW Dev, Test & Live environments. Dev build is complete, but knock-on effect still to be calculated. The EDW Implementation project will be subject to a re-plan. This will impact EST109.
Next Steps
- Complete design work.
- Commence development
The project is reporting AMBER until a) design signed off, or b) impact of EDW Implementation delay understood.
- Approved budget
- 240.0 days
- Activity this month
- 30.4 days
- Activity this year
- 75.9 days
- Activity to date
- 75.9 days
- Estimate to complete current year
- 170.2 days
- Estimate to complete future years
- 0.0 days