Report for March 2018
- Report Date
- March 2018
Achievements in Last Period
- Space & Maintenance Data Model complete.
- Space ETL design complete.
- Maintenance ETL design in progress.
- Space ETL development in progress.
Issues
- Project analysis, design phases are running behind schedule.
- Project is dependent upon the delivery of EDW Dev, Test & Live environments. The EDW Implementation project has been re-planned. This will impact EST109.
Next Steps
- Re-plan based upon refined estimates. Submit & gain approval for governance changes.
- Complete design.
- Progress development.
The project is reporting AMBER until after project re-plan and any resultant governance changes are submitted and approved.
- Approved budget
- 240.0 days
- Activity this month
- 39.5 days
- Activity this year
- 115.4 days
- Activity to date
- 143.7 days
- Estimate to complete current year
- 143.7 days
- Estimate to complete future years
- 3.4 days