Report for March 2020
- Report Date
- March 2020
Project status is moving from Suspended to Close. This was agreed with the Project Sponsor, Kyle Clark-Hay, the Estates Programme team: Jane Cameron and Zoe Stephens, IS Derrick Matheson (Programme Manager,) and Mark Ritchie (Application Development and Operations Deputy Director, Project Services) at a meeting early March 2020.
Derrick Matheson has confirmed in email on 12th March that "It is expected that Estates will restart this work although the dates for this are, as yet, unclear".
Achievements this month
- A draft "Invitation to Quote" document to engage a 3rd party supplier to support 1. define strategy and 2. plan for Estate Information and Documentation Management was reviewed by IS Programme Manager, Derrick Matheson and Mark Ritchie Application Development and Operations Deputy Director and then sent to Estates for review on 5th March with meeting agenda proposal
- Virtual Closure review exercise completed with IS Claire Bradford and Alex Carter on 23rd March to identify lessons learned that can be brought forward and availability of project documentation.
- Check complete to confirm Project documentation available on SharePoint.
Next Steps
- Project Manager to complete Closure Report and closure PMO managed activities
- Review with Project Sponsor, Kyle Clark-Hay, re-scheduled for 9th April (Issue raised - as Kyle's priority has shifted to support of COVID 19 management).
- A meeting to be scheduled for week starting 6th April PM, Programme Manager & Application Development and Operations Deputy Director, Project Services to agree on billing.
- Approved budget
- 672.0 days
- Activity this month
- 2.0 days
- Activity this year
- 132.0 days
- Activity to date
- 335.0 days
- Estimate to complete current year
- 38.0 days
- Estimate to complete future years
- 0.0 days