Project Brief

Document Sign Off

Name Project Role Date Signed Off
Grant Ferguson Project Sponsor 08/10/19
Mark Ritchie Senior Supplier 08/10/19
Karen Adamson Financial Assurance / Business Project Lead 09/10/19
Jane Cameron Estates MIS Transformation Portfolio & Programme Manager 08/10/19
Derrick Matheson IS/Estates Transformation Programme Manager 10/09/19

 

Project Info

Project
Estates Facilities Management Optimisation
Code
EST115
Programme
Z. Estates Facilities Management Programme (ECAF) - Closed
Management Office
ISG PMO
Project Manager
Marjory Howarth
Project Sponsor
Grant Ferguson
Current Stage
Close
Status
Closed
Project Classification
Transform
Start Date
01-Jun-2018
Planning Date
11-Oct-2019
Delivery Date
29-May-2020
Close Date
03-Dec-2020
Programme Priority
2
Overall Priority
Higher
Category
Discretionary